Mugu Karnali Storage — Feasibility, Bids & EOI Record (2024–2025)
- Page status
- Working page
- Updated
- 2026-05-12
Summary
Reference compilation for the 1,902 MW Mugu Karnali Storage Hydroelectric Project — Nepal's largest proposed generation asset, in pre-feasibility under Vidhyut Utpadan Company Limited (VUC) and open to public–private partnership bidding.
Key Data Points
- Capacity: 1,902 MW
- Type: Storage / pumped-storage; 10 Francis turbines
- Gross head: ~285 m
- Design annual energy: ~5,883 GWh
- River: Karnali
- District: Mugu (registry); Bajura also referenced in early materials
- Developer: Vidhyut Utpadan Company Limited (VUCL / VUC) — state-owned
- Structure: PPP, VUC seeking 51% partnership stake
- Survey licence: granted by DoED; 2-year feasibility deadline with extension possible to 5 years
- Expressions of interest (2024–2025):
- Adani Group — EOI (no formal bid as of January 2025)
- Chowdhury Group (CG Energo Pvt Ltd) — formal bid submitted, only competitor on record as of January 2025
- Planned schedule (Power Technology): construction from ~2030, COD ~2034
Relevance to Project
Primary source for Mugu Karnali's scale, schedule, bidding posture and the India-vs-Bangladesh developer interest that makes it politically visible. Notable because 1,902 MW is larger than Nepal's entire current operating hydropower fleet.
Limitations
- Pre-feasibility stage: The project is at pre-feasibility; no detailed hydrology, sediment, or seismic study outcomes are published.
- Transmission gap: A project of this scale implies new 400 kV or higher corridor infrastructure that does not yet exist; no evacuation plan is disclosed.
- Environmental/social scoping absent: No full EIA has been disclosed; the project is at the expression-of-interest stage.
- Bid landscape fluid: Only one formal bid (Chowdhury Group) is on record as of January 2025; the competitive landscape may shift.
- Schedule aspirational: The 2030 construction / 2034 COD timeline is a Power Technology projection, not a committed project schedule.