Upper Karnali Official Records — IBN and DoED (2022–2026)

Page status
Working page
Updated
2026-07-10

Open in the interactive explorer and map

Summary

This source record combines two primary Government of Nepal records relevant to the Upper Karnali Hydroelectric Project: Investment Board Nepal's 2021/22 annual report and the Department of Electricity Development's registry updated 2 July 2026. Together they document a conditional financial-close extension and the project's current administrative registry listing.

Key Findings

  • Investment Board Nepal records that the Government of Nepal approved a two-year extension of the financial-close deadline in July 2022, subject to conditions.
  • The IBN record describes the developer as being in a process to meet the negotiation conditions; it does not report financial close as achieved.
  • The DoED registry updated 2 July 2026 lists Upper Karnali HEP at 900 MW on the Karnali River, with GMR Upper Karnali Hydropower Limited as promoter.
  • The DoED page places the project in its more-than-1-MW survey-licence table. That administrative listing establishes a current registry record, not construction, financing or PPA status.

Relevance

These official records provide a primary institutional baseline for Upper Karnali and distinguish a deadline extension or registry listing from achieved financial close, lender disbursement, executed offtake or construction commencement.

Limitations

  • Neither record contains an executed financing agreement, lender effectiveness notice, construction notice to proceed, signed buyer PPA or tripartite transit approval.
  • The IBN annual-report entry is historical and cannot establish the position after its reporting period.
  • The DoED registry's licence category is administrative; it should not be inferred to be a physical delivery-stage classification.

Official Records