Upper Karnali
A 900 MW export-oriented project with a revised partner structure but no verified financial close, disbursement or construction start.
- Page status
- Working page
- Updated
- 2026-07-10
- Last reviewed
- 2026-11-04
- Review due
- 2027-02-04
Summary
A 900 MW run-of-river scheme on the Karnali, awarded to GMR in 2008 and still at an early, pre-construction stage. The project has a revised partner structure but no verified achieved financial close, disbursement or construction commencement. A June 2026 ICRA rationale records GMR 34%, SJVN 34%, IREDA 5% and NEA 27%, while continuing to describe the project as being at a very early stage of development.
Specifications
| Parameter | Value |
|---|---|
| Capacity | 900 MW |
| Status | Stalled / pre-construction; financial close not verified |
| River | Karnali (Karnali Basin) |
| Districts | Surkhet, Dailekh, Achham |
| Province | Karnali Pradesh |
| Licence awarded | 2008, via international competitive bidding |
Engineering
Upper Karnali is a run-of-river diversion scheme on the Karnali main stem — the same engineering archetype as Arun 3 but in the western Karnali basin. At 900 MW, it would be the second-largest RoR plant in Nepal after Arun-3. The project's engineering challenge is not the head or flow regime (the Karnali has reliable hydrology) but the transmission distance: 900 MW from the mid-Karnali to the Dhalkebar-Muzaffarpur export corridor requires a new 400 kV transmission spine through western Nepal.
| Parameter | Value |
|---|---|
| Type | Run-of-River |
| Annual design energy | 3,466 GWh |
| Planned export share | ~88% |
Output
Design annual energy is reported at approximately 3,466 GWh, with a large export orientation. Public statements have cited several possible Bangladesh volumes, but the wiki has not verified an executed, bankable offtake agreement and the approvals needed to wheel that electricity through India.
The Bangladesh component makes Upper Karnali the test case for Nepal's "second neighbour" trade strategy — but no PPA has yet closed. The Bangladesh figures have shifted repeatedly: 250 MW, 300 MW, 500 MW, and 200 MW have all been quoted at different moments between 2017 and 2025. A moving target is not a market — it is a signal that the tri-nation transmission architecture (Nepal → India → Bangladesh) remains unresolved.
| Parameter | Value |
|---|---|
| Annual design energy | 3,466 GWh |
| Planned export share | ~88% |
| India export | Primary target (no firm PPA) |
| Bangladesh export | Multiple quantities announced; bankable executed PPA not verified |
Governance
The current reported ownership structure is GMR 34%, SJVN 34%, IREDA 5% and NEA 27%. Ownership participation is not equivalent to financing approval, financial close or funds disbursed. See Hydro-Geopolitics.
The 2008 international competitive bidding awarded the project to GMR under a Project Development Agreement (PDA) — a bilateral contract between the Government of Nepal and the developer that gave GMR exclusive development rights with defined milestones. GMR failed to meet the financial closure deadline; the government extended it repeatedly. Each extension eroded the credibility of the PDA model: if deadlines are routinely extended, they are not deadlines.
| Parameter | Value |
|---|---|
| Developer | GMR Upper Karnali Hydropower Limited |
| Reported ownership (Jun 2026) | GMR 34% · SJVN 34% · IREDA 5% · NEA 27% |
| Concession type | PDA (international competitive bidding, 2008) |
| Original financial close deadline | ~2014 (extended repeatedly) |
Schedule
Eighteen years have passed since the 2008 award without construction commencement. The project should be monitored through evidence of financial close, offtake, land and access readiness, notice to proceed and physical works—not through deadline-extension announcements.
| Parameter | Value |
|---|---|
| Licence awarded | 2008 |
| Financial closure | Not achieved (as of 2026) |
| Completion | ~0% |
| Construction | Not started |
Current Status and Performance Provenance
As of 10 July 2026: stalled / pre-construction. The partner structure has changed, but the current primary evidence does not show financial close, lender disbursement or a construction notice to proceed.
| Dimension | Current position | Evidence date |
|---|---|---|
| Ownership | GMR 34%, SJVN 34%, IREDA 5%, NEA 27% | 29 Jun 2026 |
| Financial close | Not verified | 29 Jun 2026 |
| Construction | Very early development stage; physical works not established | 29 Jun 2026 |
| Offtake | Prospective export arrangements; bankable status not verified | 10 Jul 2026 review |
Recent Updates
| Date | Update | Source |
|---|---|---|
| 29 Jun 2026 | ICRA recorded the current proposed ownership split and described the project as very early stage | ICRA rating rationale |
Active Blockers
| Blocker | Prevents | Verification rule |
|---|---|---|
| Achieved financial close and disbursement are not evidenced | Notice to proceed and major construction | Require lender or project-company closing disclosure |
| Bankable power offtake is not evidenced | Revenue certainty and financing | Require executed PPA and applicable approvals |
| Export evacuation remains a critical dependency | Delivery of contracted electricity | Require committed project-to-market transmission path |
The GMR Saga: Timeline of an Unbuilt Project
| Year | Event |
|---|---|
| 2008 | GMR wins international competitive bidding for 900 MW Upper Karnali; PDA signed with Government of Nepal |
| 2008–2014 | GMR undertakes survey and feasibility studies; financial closure targeted for ~2014 |
| 2014 | High-level committee raises concerns about downstream irrigation impacts on India's Ganga system; objection stalls progress |
| 2015–2017 | PDA deadlines extended; GMR begins discussions with Bangladesh for export PPA |
| 2017 | Bangladesh PPA announced — initially 500 MW, later adjusted to 250–300 MW range |
| 2018–2020 | Further PDA extensions; financial closure repeatedly deferred |
| 2020–2022 | COVID-19 disruptions; project enters "force majeure" discussions |
| 2023–2024 | Supreme Court of Nepal intervenes: rules that open-ended PDA extensions are not permissible; grants only 186-day allowance for time lost under court's own interim orders |
| 2025 | SJVN and IREDA join equity stack alongside GMR; NEA takes a stake |
| 2026 | ICRA records revised ownership participation while describing the project as very early stage |
The dated record shows repeated attempts to resolve a linked financing, offtake, transmission and deadline problem. The revised ownership may change the sponsor base, but it does not itself prove that any of those milestones has closed.
The Supreme Court Intervention
The Supreme Court's ruling is significant beyond Upper Karnali. By limiting extensions to 186 days (for time lost under the court's own interim orders), the court signaled that the PDA-extension cycle — where projects are awarded, deadlines are missed, extensions are granted, and nothing is built — is not legally sustainable. This has implications for:
- Other stalled PDAs: West Seti Hydroelectric Project (750 MW, NHPC), Arun 3 (already executing, less relevant)
- Future licensing: the Investment Board Nepal's PDA framework may need tighter milestone enforcement
- Investor confidence: the ruling cuts both ways — it disciplines developers to meet deadlines, but also makes Nepal a riskier jurisdiction if deadlines are seen as infeasible
The Bangladesh Question
Upper Karnali's Bangladesh PPA has been "live" since 2017 but has never closed. The underlying problem is not the commercial terms — Bangladesh needs power and Nepal has it — but the transmission architecture. Exporting from Nepal to Bangladesh requires wheeling power through India's grid, which requires:
- A Nepal-India cross-border transmission agreement (Upper Karnali → Muzaffarpur or equivalent)
- An India-Bangladesh cross-border transmission agreement (existing Baharampur–Bheramara link, 1,000 MW, operational since 2013)
- A tri-nation wheeling agreement (Nepal → India → Bangladesh) — no precedent exists at this scale
The India-Bangladesh link exists, but the Nepal-India link for Upper Karnali does not. Until the 400 kV Karnali corridor is built from the project site to the Indian border, the Bangladesh PPA is a promise without a delivery mechanism. See Nepal Transmission System — 400 kV Landscape & Cross-Border Plan (2025).
Significance
Upper Karnali is the twin case to Arun 3 — same licence era, similar capacity, same India-developer / export-first model — but with the opposite outcome. Arun-3 is at 74% physical progress; Upper Karnali has been at "about to reach financial closure" for a decade. Reading the two projects together is how you understand the variance in Nepal's India-developed export class: the contract is not the product, execution is.
The project also marks how Hydro-Geopolitics has widened in Nepal's hydropower conversation. The original export target was India, while successive Bangladesh proposals make Upper Karnali a test case for tri-nation energy trade whose bankable arrangements remain unverified.
The revised ownership brings Indian state-owned entities and NEA into the project company alongside GMR. The monitored distinction is that equity participation is not the same milestone as committed project debt or financial close.
Comparison: Arun-3 vs Upper Karnali
| Parameter | Arun-3 | Upper Karnali |
|---|---|---|
| Licence awarded | 2008 | 2008 |
| Capacity | 900 MW | 900 MW |
| Developer | SJVN (India, state-owned) | GMR (India, private) |
| Status | Under construction; progress must be read with its evidence date | Not started |
| COD | Target has moved; verify against current SJVN disclosure | No verified date |
| Financial closure | Achieved | Not achieved |
| Export PPA | India (firm) | None (India uncertain, Bangladesh unclosed) |
| Transmission | Dedicated evacuation line under delivery with the project | Project-to-market corridor not committed in the current record |
| Years to construction | ~10 | 18+ and counting |
The comparison isolates the variables: same basin (Koshi vs Karnali), same era (2008), same model (PDA, export-first). The difference is developer — SJVN is a state-owned Indian utility with sovereign backing and a balance sheet that can absorb construction risk; GMR is a private conglomerate whose energy portfolio shifted substantially after 2008. See Buildability for why developer identity matters more than project design.
Limitations & Controversies
Eighteen years without a turbine. The 2008 licence award predates the current Nepal Electricity Authority (NEA) grid code in some dimensions; deadlines have been extended repeatedly. The Supreme Court ultimately ruled against open-ended extensions, granting only a 186-day allowance for time lost under its own interim orders — a signal that the judiciary no longer accepts the PDA-extension cycle as routine.
Bangladesh transmission dependency. Even if a final PPA closes, the 200–500 MW export to Bangladesh depends on a Nepal–India–Bangladesh transmission corridor that is still under development. Upper Karnali's export model contains an unresolved infrastructure prerequisite that is not on its balance sheet but is on its critical path. The India-Bangladesh Baharampur–Bheramara link exists, but the Nepal-India segment does not.
Downstream irrigation overhang. A 2014 high-level committee raised concerns about impacts on downstream irrigation in India's Ganga system. That objection was never fully resolved, only procedurally managed, and resurfaces in each PDA extension debate. The concern is structural: 900 MW of Karnali diversion reduces flow in the Ghaghara, which is a major irrigation source for Uttar Pradesh.
GMR Group's execution posture. Unlike SJVN, GMR is a private Indian conglomerate whose project pipeline has shifted substantially since 2008. GMR's energy portfolio now includes domestic Indian thermal and renewable projects, airport infrastructure, and highways — hydropower in Nepal is one of many competing capital allocations. Whether GMR remains the right primary sponsor — now that SJVN and IREDA are in the equity stack — is an open strategic question that Nepal has not formally asked.
Transmission gap. The 400 kV Karnali corridor from the project site to the Dhalkebar-Muzaffarpur export point does not exist. Building it requires coordinated investment from Nepal and India across some of Nepal's most rugged terrain. Until this corridor is committed, Upper Karnali is Stranded Generation.
Official Visual Source Gap
Upper Karnali is still unusually thin on stable public document figures. The Investment Board Nepal project and factsheet pages remain visible in search indexes, but the live page and factsheet download currently resolve to 404s, while the active GMR project page exposes basic project text without a reusable layout plate or site figure.
This page avoids generic valley scenery in both the top strip and body until a durable brochure, E&S disclosure, or layout PDF is recovered from the official source stack.
Tracked official references:
- Investment Board Nepal project page
- Investment Board Nepal factsheet page
- GMR Upper Karnali project page
See also
- Karnali Basin
- Arun 3
- Hydro-Geopolitics
- Stranded Generation
- Run-of-River Hydropower
- Mugu Karnali Storage HEP
- Nepal Transmission System — 400 kV Landscape & Cross-Border Plan (2025)
- Buildability
- Map Inventory