NEA Substation Capacity FY 2076/77

Page status
Working page
Updated
2026-05-12

Open in the interactive explorer and map

Summary

This data page records NEA's FY 2076/77 high-voltage transformer capacity and named under-construction substation queue from the Transmission Directorate annual-book appendix.

The annual book's appendix gives a rare structured view of both the installed high-voltage transformer base and the next wave of substation expansion under construction. Together, they show why NEA was still in a catch-up phase even as generation was accelerating.

Headline Totals

Metric Value
Installed HV transformer capacity, FY 2076/77 4299.7 MVA
YoY increase 364.4 MVA
Under-construction HV substation capacity 5550.5 MVA

Installed Capacity by Voltage Class

Voltage ratio Transformer count FY 2076/77 capacity (MVA) YoY increment (MVA)
220/132 2 320.0 0.0
132/66 11 522.9 0.0
132/33 51 1889.0 170.5
132/11 17 462.5 97.5
66/33 2 42.5 17.5
66/11 32 584.5 10.5
33/11 37 478.3 68.4

Named Under-Construction Substations

Project Substation Voltage ratio Capacity (MVA) Expected completion
Hetauda–Dhalkebar–Inaruwa 400 kV Expansion Dhalkebar 400/220 945 2020/21
Chilime–Trishuli 220 kV TL Chilime 220/132, 132/33 370 2020/21
Trishuli 3B Hub Substation Trishuli 3B Hub 66/11 370 2020/21
Hetauda–Bharatpur 220 kV TL New Bharatpur (Aaptari) 132/33 22.5 2020/21
Singati–Lamosanghu 132 kV TL Singati 132/33 30 2020/21
Ramechhap–Garjyang–Khimti 132 kV TL Garjyang 132/33 30 2020/21
Kushaha–Kataiya 132 kV Second Circuit Kushaha 132/11 22.5 2020/21
Dordi Corridor 132 kV TL Kirtipur 132/11 10 2020/21
Butwal–Lumbini 132 kV TL Mainahiya 132/33, 33/11 106 2020/21
Koshi Corridor 220 kV TL Tumlingtar 220/132, 132/33 260 2020/21
Koshi Corridor 220 kV TL Baneshwor 220/33 60 2020/21
Koshi Corridor 220 kV TL Basantapur 220/132, 132/33 230 2020/21
Ramechhap–Garjyang–Khimti 132 kV TL New Khimti 220/132 200 2020/21
Burtibang–Paudi Amarai–Tamghas–Sandhikharka–Gorusinghe 132 kV TL Burtibang 132/33 30 2020/21
Burtibang–Paudi Amarai–Tamghas–Sandhikharka–Gorusinghe 132 kV TL Paudi Amarai 132/33 30 2020/21
Burtibang–Paudi Amarai–Tamghas–Sandhikharka–Gorusinghe 132 kV TL Tamghas 132/33 30 2020/21
Burtibang–Paudi Amarai–Tamghas–Sandhikharka–Gorusinghe 132 kV TL Sandhikharka 132/33, 33/11 38 2020/21
Burtibang–Paudi Amarai–Tamghas–Sandhikharka–Gorusinghe 132 kV TL Motipur 132/33, 33/11 38 2020/21
Kushaha–Biratnagar 132 kV TL Biratnagar 132/33, 33/11 142 2020/21
Nawalpur 132 kV Substation Nawalpur 132/33, 33/11 79 2020/21
Sunwal 132 kV Substation Sunwal 132/33, 132/11 148.5 2020/21
Hetauda–Dhalkebar–Inaruwa 400 kV Expansion Hetauda 400/220 500 2021/22
Hetauda–Dhalkebar–Inaruwa 400 kV Expansion Inaruwa 400/220 945 2021/22
NIETTP / Hetauda–Dhalkebar–Inaruwa Hetauda 220/132, 132/11 210 2021/22
NIETTP / Hetauda–Dhalkebar–Inaruwa Inaruwa 220/132, 220/33 326 2021/22
Koshi Corridor 220 kV TL Dhungesanghu 132/33 30 2021/22
New Modi–Lekhnath 132 kV TL Lahachowk 132/33, 33/11 38 2021/22
Lamahi–Ghorahi 132 kV Expansion Ghorahi 132/33 63 2021/22
Keraun 132 kV Substation Keraun 132/33, 132/11 148.5 2021/22
Dhalkebar–Loharpati 132 kV TL Loharpatti 132/33, 132/11, 33/11 98.5 2021/22

Why It Matters

Coverage / Method

The installed-capacity table and under-construction queue are drawn from the NEA Transmission Directorate annual-book appendix for FY 2076/77. The page preserves voltage ratios, transformer counts, MVA capacity, year-over-year increment where reported, project/substation names, and expected completion years from that source.

Caveats

The annual-book appendix is a historical snapshot and should not be read as current substation capacity. Under-construction entries are pipeline records from the source year, not confirmation that every substation was commissioned on the expected schedule or at the listed capacity.