Kali Gandaki A — ADB Performance Evaluation & Wikipedia
- Page status
- Working page
- Updated
- 2026-05-11
Summary
Reference compilation for the 144 MW Kali Gandaki A plant at Mirmi, Syangja — combining the ADB's post-project performance evaluation (the plant was ADB/JBIC co-financed) with the Wikipedia-aggregated operational history and the recent NEA rehabilitation tender.
Key Data Points
- Installed: 144 MW (3 × 48 MW Toshiba Francis units)
- Gross head: 115 m
- Design annual energy: ~860 GWh
- Average actual output: ~592 GWh/year since commissioning
- Construction: 1997–2002; turbines commissioned Mar / Apr / May 2002
- Total cost: USD 354.8 million (~NPR 50 billion at the time)
- Funding: ADB + Japan Bank for International Cooperation
- Owner/operator: Nepal Electricity Authority (NEA)
- Location: Mirmi, Syangja District; Kali Gandaki–Andhikhola confluence
- Status (2024): Nepal sought design & supervision consultants for a rehabilitation of the three-unit plant
Relevance to Project
Primary source for Kali Gandaki A's capacity, head, generation, funding stack and rehabilitation posture. Useful benchmark for Nepali- developed, Nepali-dispatched hydro at moderate scale — the foil to India-developed export projects like Arun 3 and Upper Karnali.
What This Source Does Not Cover
- Current reservoir (pondage) operation strategy
- Full seasonal generation shape
- Detailed explanation of the >250 GWh gap between design energy
(
860 GWh) and average actual output (592 GWh)
Limitations
- Compilation, not primary field data. Combines ADB post-project evaluation, Wikipedia operational history, and Renewable Energy World reporting — different levels of rigor across sources.
- Design-vs-actual gap unresolved. The >250 GWh/year shortfall between design (
860 GWh) and average actual output (592 GWh) is documented but not diagnostically explained. - Rehabilitation snapshot only. Covers the 2024 rehabilitation tender announcement but not the subsequent procurement, contractor selection, or scope finalization.