Khimti–Dhalkebar 220 kV Hydropower Corridor

Page status
Registry record
Updated
2026-05-11

Open in the interactive explorer and map

Summary

The original "IPP-to-grid" line in Nepal. Built to evacuate Khimti -I — the country's first large IPP (1996 PPA, 2000 commissioning) — toward the central grid at Dhalkebar. Its history mirrors the birth of private hydropower in Nepal and the long legal and political battles that surround it.

Key Facts

Parameter Value
Voltage 220 kV (double circuit)
Status Operational
Length ~75 km
Owner Nepal Electricity Authority (NEA)
Terminals Khimti substation (Dolakha) · Dhalkebar substation (Dhanusha)
Commissioned 2016
Financing World Bank (IDA) — Nepal India Regional Trade and Transportation Project
Corridor ID khimti_dhalkebar_220

Significance

  • First line built for an IPP. Before Khimti -I, Nepal had no practice of building high-voltage lines specifically to evacuate independent power producers — the Khimti–Dhalkebar project was the template.
  • Legal precedent. The project's land-acquisition lawsuits (2011–15) set Nepali case law on the public-interest use of private land for transmission.
  • Feeds the export funnel. Terminates at Dhalkebar, which is also the origin of Hetauda–Dhalkebar–Inaruwa 400 kV Backbone and Dhalkebar–Muzaffarpur 400 kV Cross-Border Interconnection. Roughly half of Nepal's exportable hydropower still routes through it.

Limitations & Controversies

  • Capacity is effectively full. Contracted flow from Khimti-I + downstream IPPs exceeds 300 MW in peak monsoon; a second 220 kV or 400 kV reinforcement from the Tamakoshi–Khimti cluster has been studied but not funded.
  • Sediment disruption risk. The corridor crosses steep Sindhupalchok and Dolakha terrain; landslide damage to tower foundations was flagged in the 2023 monsoon assessment.