Inaruwa–Purnea 400 kV Cross-Border Interconnection

Page status
Registry record
Updated
2026-05-11

Open in the interactive explorer and map

Summary

The planned third 400 kV Nepal–India link, critical to evacuating the Arun 3 export block (900 MW) and later Upper Karnali-tier eastern generation. Currently in implementation-setup phase — the route exists on paper and in the bilateral MoU record, but construction has not begun.

Key Facts

Parameter Value
Voltage 400 kV
Status Implementation setup
Nepal terminal Inaruwa substation (Sunsari) — eastern terminus of Hetauda–Dhalkebar–Inaruwa 400 kV Backbone
India terminal Purnea (Bihar)
Length ~160 km total (≈50 km Nepal, ≈110 km India)
Primary purpose Evacuation of Arun 3 to the Indian grid
Status driver Tied to Arun 3 COD — originally 2023, now 2027+
Interconnection ID inaruwa_purnea

Significance

Limitations & Controversies

  • Schedule tied to Arun-3. Each slip in Arun-3 construction pushes the cross-border line as well — and vice versa.
  • Environmental route. Alignment through Sunsari and Saptari districts still contested in local consultations.
  • Indian-side approvals. Bihar state government concurrence and CEA tariff framework are the remaining gating items.

See also