Gorakhpur–New Butwal 400 kV Cross-Border Interconnection
- Page status
- Working page
- Updated
- 2026-07-10
Open in the interactive explorer and map
Summary
Nepal's second major 400 kV cross-border link, under construction
between New Butwal and Gorakhpur. POWERGRID's FY 2024/25 annual report
records a 50:50 NEA–POWERGRID joint venture for the Indian portion. The
Nepal and India sections, terminal works and the domestic New Butwal
evacuation path must be monitored separately; a project-wide target
year is not proof that all components are ready.
Key Facts
| Parameter |
Value |
| Voltage |
400 kV |
| Status |
Under construction |
| Nepal terminal |
New Butwal (Rupandehi) |
| India terminal |
Gorakhpur (Uttar Pradesh) |
| Length |
130 km (18 km Nepal + ~112 km India) |
| Indian-side owner |
Butwal-Gorakhpur Cross Border Power Transmission Limited (50:50 NEA–POWERGRID JV) |
| Nepal-side owner |
Nepal Electricity Authority (NEA) |
| Commissioning |
No firm current project-wide date established |
| Interconnection ID |
gorakhpur_new_butwal |
Current Status
As of 10 July 2026: under construction. The segment record
separates the two countries and treats synchronized testing and New
Butwal's domestic-grid connection as explicit dependencies.
| Segment |
Status |
Evidence date |
Dependency |
| New Butwal–Nepal/India border |
Under construction |
Verified 10 Jul 2026 |
New Butwal terminal and domestic evacuation readiness |
| Nepal/India border–Gorakhpur |
Under construction |
POWERGRID FY 2024/25 |
Synchronized Nepal-side completion and cross-border testing |
Recent Updates
Active Blockers
| Blocker |
Prevents |
Monitoring requirement |
| Nepal and India segment schedules may diverge |
Synchronized commissioning |
Country- and package-level progress evidence |
| New Butwal terminal and domestic evacuation readiness |
Transfer of cross-border capacity into Nepal's grid |
Integrated testing and energisation record |
| Current trading and transmission-charge arrangements are not documented in this dossier |
Commercial use |
Applicable approved agreements and regulatory orders |
Significance
- Redundancy for the eastern link. Full N-1 cross-border security
for the first time once both operate in parallel.
- Western evacuation. Opens a direct export door for
Gandaki Basin and Karnali Basin generation — which has
historically had no outlet matching its latent capacity.
- MCA corridor payoff. The US-funded MCA Central 400 kV Corridor (Lapsiphedi–Ratmate–Hetauda–Damauli–Butwal) spine has
little export value without this link — the two projects are
schedule-linked in NEA's integrated resource plan.
Limitations & Controversies
- Schedule history. Public target dates have moved. The monitoring
record therefore requires dated segment evidence instead of carrying
the latest announced year forward as a firm date.
- Nepal-side readiness. New Butwal substation 400 kV bays await
final MCA corridor completion; misalignment of the two projects
could strand capacity on either side.
- Tariff mechanism. Cross-border trading charges for this link have
not yet been fully negotiated under the 2021 cross-border guidelines.