Gorakhpur–New Butwal 400 kV Cross-Border Interconnection

Page status
Working page
Updated
2026-07-10

Open in the interactive explorer and map

Summary

Nepal's second major 400 kV cross-border link, under construction between New Butwal and Gorakhpur. POWERGRID's FY 2024/25 annual report records a 50:50 NEA–POWERGRID joint venture for the Indian portion. The Nepal and India sections, terminal works and the domestic New Butwal evacuation path must be monitored separately; a project-wide target year is not proof that all components are ready.

Key Facts

Parameter Value
Voltage 400 kV
Status Under construction
Nepal terminal New Butwal (Rupandehi)
India terminal Gorakhpur (Uttar Pradesh)
Length 130 km (18 km Nepal + ~112 km India)
Indian-side owner Butwal-Gorakhpur Cross Border Power Transmission Limited (50:50 NEA–POWERGRID JV)
Nepal-side owner Nepal Electricity Authority (NEA)
Commissioning No firm current project-wide date established
Interconnection ID gorakhpur_new_butwal

Current Status

As of 10 July 2026: under construction. The segment record separates the two countries and treats synchronized testing and New Butwal's domestic-grid connection as explicit dependencies.

Segment Status Evidence date Dependency
New Butwal–Nepal/India border Under construction Verified 10 Jul 2026 New Butwal terminal and domestic evacuation readiness
Nepal/India border–Gorakhpur Under construction POWERGRID FY 2024/25 Synchronized Nepal-side completion and cross-border testing

Recent Updates

Date Update Source
31 Mar 2025 POWERGRID recorded the 50:50 implementing JV and its paid-up capital POWERGRID FY 2024/25 annual report
31 Jul 2025 The stated 22-month PMC period for the Indian portion elapsed; no public completion outcome is established by the reviewed POWERGRID records POWERGRID FY 2023/24 annual report
2 Jun 2023 India and Nepal jointly carried out the groundbreaking Embassy of India record

Active Blockers

Blocker Prevents Monitoring requirement
Nepal and India segment schedules may diverge Synchronized commissioning Country- and package-level progress evidence
New Butwal terminal and domestic evacuation readiness Transfer of cross-border capacity into Nepal's grid Integrated testing and energisation record
Current trading and transmission-charge arrangements are not documented in this dossier Commercial use Applicable approved agreements and regulatory orders

Significance

Limitations & Controversies

  • Schedule history. Public target dates have moved. The monitoring record therefore requires dated segment evidence instead of carrying the latest announced year forward as a firm date.
  • Nepal-side readiness. New Butwal substation 400 kV bays await final MCA corridor completion; misalignment of the two projects could strand capacity on either side.
  • Tariff mechanism. Cross-border trading charges for this link have not yet been fully negotiated under the 2021 cross-border guidelines.