Upper Arun Hydroelectric Project

Page status
Working page
Updated
2026-05-12

Open in the interactive explorer and map

ERT survey at IkhuwaKhola HPP (IKHPP) Core Drilling at JawaTila
ERT survey at IkhuwaKhola HPP (IKHPP) Core Drilling at JawaTila

Summary

Upper Arun is a 1,063.36 MW peaking run-of-river hydropower project in Bhotkhola Rural Municipality, Sankhuwasabha, promoted through Upper Arun Hydro-Electric Limited, an NEA subsidiary.

The project has moved beyond the older FY 2019/20 study-stage description: UAHEL now publishes current project parameters, including rated discharge, rated head, average annual energy, a 400 kV evacuation link to Haitar, and a target schedule that enters construction in 2026 and reaches completion in December 2032.

Specifications

Field Value
Project type Peaking run-of-river
Location Bhotkhola Rural Municipality, Sankhuwasabha District, Koshi Province
Installed capacity 1,063.36 MW, including 2.36 MW eco-flow plant
Rated discharge 235.44 m3/s
Rated head 508.26 m
Average annual energy 4,518 GWh, excluding 18 GWh from eco-flow turbine
Minimum peaking 697 MW for six hours daily at Q95 inflow
Main generation units Six Pelton turbines
Evacuation plan 5.8 km 400 kV double-circuit line to Haitar substation
Target construction entry 2026
Target completion December 2032

Why It Matters

  • Upper Arun is a good example of how long the pipeline is between identifying a large Himalayan project and reaching bankable execution.
  • It belongs with Arun 3 and Nepal Transmission System — 400 kV Landscape & Cross-Border Plan (2025) because any future Upper Arun build would need both project delivery and corridor evacuation to line up.
  • Its peaking design makes it materially different from ordinary run-of-river MW in the Arun basin, though this does not remove financing, access-road, environmental, and evacuation risks.

Limitations & Controversies

Preparation-stage schedule. UAHEL publishes a target construction start in 2026 and target completion in December 2032, but those are project targets rather than evidence of financial closure, PPA execution, or construction commencement.

Corridor dependency. Any future Upper Arun build would need both project delivery and corridor evacuation to line up with Arun 3 infrastructure and the Nepal Transmission System — 400 kV Landscape & Cross-Border Plan (2025) backbone. The project cannot advance independently of these larger system decisions.

Developer-source boundary. The current specifications come from UAHEL's own project page. They should be cross-checked against NEA annual reports, DoED license records, lender documents, and environmental approvals before being treated as final bankable parameters.