Summary

The revised national hydropower potential assessment. Supersedes the older 83,000 MW theoretical figure with updated screening. Provides basin-level gross and techno-economic potential breakdowns.

Key Data Points

  • Revised gross potential: 72,544 MW (down from legacy 83,500 MW)
  • Techno-economic potential: 32,680 MW
  • Basin distribution of gross potential:
  • ~94% of gross potential is in the three major Himalayan basins

Limitations

  • Screening opacity: Full Multi-Criteria Analysis methodology and sensitivity parameters are not transparent in the public version.
  • Gross vs techno-economic: The 72,544 MW gross potential is a theoretical ceiling; the 32,680 MW techno-economic potential is the more honest planning baseline.
  • Legacy figure persistence: The older 83,000 MW figure remains politically prominent despite this revision.
  • Exclusions: Does not account for climate-adjusted hydrology, sediment risk, or buildability constraints that would reduce realisable potential below techno-economic estimates.

Relevance to Project

The definitive source for Hydropower Potential Categories. Only surfaced the revised 72,544 MW figure — public summaries used the legacy 83,000 MW. The basin concentration data (94% in three basins) is central to the strategic argument.