Unresolved Questions

A current register of evidence gaps, data conflicts and monitoring priorities that materially limit claims about Nepal's electricity system.

Page status
Verified core
Updated
2026-11-04
Last reviewed
2026-11-04
Review due
2027-02-04

Open in the interactive explorer and map

Areas where public evidence remains thin, source definitions conflict, or more granular data would materially improve the hub. Project-specific active blockers are now also maintained in the monitoring registry.

Research Gaps

# Gap Why It Matters Status
1 DHM long time-series discharge data by tributary Validate basin-level flow claims at project resolution OPEN — likely locked behind institutional access
2 Monthly import-export time series Strengthen Seasonal Arbitrage Trap argument beyond annual aggregates FILLED — month-by-month GWh table for FY 2079/80 (~2022/23), combined with FY 2025/26 NPR monthly revenue data. See Electricity Trade Time Series
3 Plant-level curtailment and outage data Quantify Stranded Generation precisely OPEN — public transmission reports provide daily aggregates, while the Generation Directorate operational-report page is not yet populated; plant availability, dispatch events and reason codes remain unavailable. See NEA Operational-Reporting Portals (2026)
4 NEA financial health Audited accounts, debt burden, PPA liability exposure FILLED — FY 2024/25 financials and May 2025 white paper data in Nepal Electricity Authority (NEA)
5 Project-level sediment and geology assessments Move Sediment as Design Constraint from general to specific OPEN — requires individual project EIAs and current safeguard instruments
6 Demand-side load shape (hourly/daily) Critical for system design and Firm Power analysis PARTIALLY FILLED — evening peak timing (18:30-19:25), peak import-at-peak magnitude (643 MW in Falgun 2080), and monthly import totals are documented. Full hourly load curve is not public. See Domestic Electricity Demand Distribution
7 Post-2024 Bangladesh trade route status Scale-up trajectory for buyer diversification FILLED — full page at Nepal–Bangladesh Electricity Trade Route
8 Chinese-linked project status Earlier public summaries left uncertainty unresolved FILLED — West Seti (CTG withdrew 2018, NHPC now), Budhigandaki (Gezhouba blocked, domestic). See West Seti Hydroelectric Project, Budhigandaki Hydroelectric Project
9 Environmental/social impact data on storage candidates Displacement, ecological, downstream effects of Budhigandaki Hydroelectric Project, Dudhkoshi Storage Hydroelectric Project PARTIALLY FILLED — Budhigandaki resettlement (8,117 households, NPR 42.65B compensation) now documented
10 Comparison with other mountain hydro systems Norway, Switzerland, Bhutan Hydropower Model, Laos with actual data FILLED — Mountain Hydro System Comparison created with IHA/StatRanker/Oxford data
11 Representative RoR/PRoR/reservoir development cohort Test the multi-factor explanation for Operating Fleet Is Overwhelmingly RoR/PRoR, Not True Storage without assigning one PPA, policy, incentive, institution, or actor as the cause OPEN — compare development time, capital, PPA form, risk allocation, approvals, land, safeguards, transmission, public support, and completion outcomes under a declared sampling rule
12 Implementation of the reservoir PPA directive Distinguish an approved framework from actual procurement, finance, construction, and dependable service OPEN — official text is verified at ERC Reservoir-Based Generating Station Electricity Purchase and Sale Directive 2082; project-level ERC applications, decisions, signed PPAs, financing close, and service obligations remain to be tracked

Data Conflicts Needing Resolution

Data Point Conflict Recommended Handling
Installed capacity NEA annual report, DoED registry, and hydro-only totals answer different questions Use 3,591.262 MW total / 3,389.912 MW hydro for NEA FY 2024/25, and 3,791.874 MW for the DoED Apr 10, 2026 >1 MW registry
Hydro MW Hydro-only totals can be confused with total installed capacity Use 3,389.912 MW in data pages that mean hydro-only FY 2024/25
Trade totals FY 2024/25 NEA narrative, monthly balance, and trade chart totals differ Keep all three NEA views with labels: narrative 1,681 / 2,380, monthly table 1,712 / 2,380, trade chart 1,711.5272 / 2,331.7360
Potential (gross) Legacy 83,000 MW slogan vs WECS 2019 reassessment Keep both: 83k legacy slogan + 72,544 MW WECS 2019 gross reassessment
Potential (techno-economic) Different filters produce different ranges Use 32,680 MW from WECS 2019 where the exact reassessment is needed
Current storage (MCM) Active and gross reservoir volume are mixed in public summaries Keep both: 85 MCM active / 130-150 MCM total
Cross-border capacity Rounded older values compete with project-specific approvals Use 1,141 MW approved, with older ~1,000 MW references retained only as rounded framing
System losses Source year and accounting frame differ Use 12.26% total system loss for NEA FY 2024/25; older ~12.7% references belong to the prior report framing
Basin discharge baselines Gauge points and basin-border models are not interchangeable Always label measurement point: gauge (e.g. Chatara/Chisapani) vs WECS border model
Electricity access Consumer-category shares and access/service indicators are easily conflated Use 97.6% national grid coverage for NEA FY 2024/25; do not treat the domestic-consumer share as household electrification
Fleet split World Bank and ERC/ECA descriptions, older detailed splits, and the current DoED register use different dates and taxonomies Use predominantly RoR/PRoR for the structural statement; use 106 MW / 2.71% only for the Kulekhani seasonal-service cascade against the June 2026 DoED register; do not classify the 97.29% complement by subtraction
Reservoir PPA framework The 2025 ERC/ECA paper is a proposal, while the 2082 directive is approved official text Cite ERC/ECA Discussion Paper on Storage Hydro PPA Pricing (2025) for discussion-paper findings and ERC Reservoir-Based Generating Station Electricity Purchase and Sale Directive 2082 for regulatory status; do not treat proposals as adopted terms or issuance as delivered capacity
Per-capita electricity Different source years create a range Use 370-465 kWh as a range unless a specific source year is named

Claims Still Needing Verification

Claim Area What's Needed Status
400/220 kV corridor status Current status of internal transmission buildout PARTIALLY FILLED — corridor evidence exists, but current Hetauda–Dhalkebar completion, energisation, remaining works and transfer capacity are unverified. See Transmission and Delivery Are Material Immediate Monetization Constraints and Hetauda–Dhalkebar–Inaruwa 400 kV Backbone
Plant-wise export approvals Sharpen firm-vs-surplus export argument PARTIALLY FILLED — 941 MW approved from 28 projects; India CEA data confirms project-level approvals
Realized export prices Firm up Seasonal Arbitrage Trap economics FILLED — NPR 7.11/unit export avg, 6.40 US cents Bangladesh, in Electricity Trade Time Series
Pancheshwar status Refine Pancheshwar Multipurpose Project treatment PARTIALLY FILLED — current official records support the 6,720 MW scheme basis, but an agreed final DPR, detailed benefit allocation and current joint minutes remain open. See Pancheshwar Multipurpose Project
China-linked projects Keep Hydro-Geopolitics accurate FILLED — CTG withdrew West Seti 2018, Gezhouba blocked from Budhigandaki; updated in Hydro-Geopolitics, West Seti Hydroelectric Project, Budhigandaki Hydroelectric Project
Causes of RoR/PRoR dominance Quantify the contribution of contract, capital, approval, project-scale, safeguard, transmission, market, and state-capacity factors across periods OPEN — current evidence supports a source-bounded multi-factor account but not a single-cause claim
Kulekhani output drop Explain why the only seasonal-storage cascade generated 92 GWh in FY 2025/26 against about 280 GWh in FY 2024/25 (NEA energy balances); determine whether automation works, outages, low inflow or operating policy caused it OPEN — the FY 2025/26 report notes Kulekhani I/II automation in final testing but gives no cause

Current Monitoring Priorities

Area Evidence needed Current handling
Upper Tamakoshi Current Rolwaling package progress, stop/restart evidence and commissioning schedule PARTIALLY FILLED — April–May 2026 filings have been ingested and financial lines reconciled; they do not establish current package percentage, a stop/restart date or commissioning schedule
Budhigandaki Hydroelectric Project Approved DPR/salient features, financing, compensation and resettlement disclosures OPEN — current procurement notices do not establish construction readiness
Upper Karnali Executed financial close, bankable offtake and current PDA/court milestone OPEN — proposed partner structure is not financial close
Dudhkoshi Storage Hydroelectric Project Financing approval and current safeguard instruments, including GLOF design basis OPEN — proposed financing and early design material do not establish implementation
Arun 3 and Gorakhpur–New Butwal 400 kV Cross-Border Interconnection Dated, component-level generation, evacuation-line and cross-border commissioning progress OPEN — overall target dates are not sufficient evidence of synchronized delivery
IPO Hydropower Bailout Issuer-by-issuer prospectus extraction, offer completion and post-offer use of proceeds OPEN — SEBON records now identify a primary-document trail, but no audited sector-wide inventory yet