Solar Fleet Inventory

Page status
Working page
Updated
2026-04-23

Open in the interactive explorer and map

Summary

The utility-scale solar analogue of Hydropower Fleet Composition. The full "what is on the ground, what has PPA, what is being built, what is tendered" picture for Nepal solar — the frame for every capacity-planning argument in the wiki.

Coverage / Method

  • Data sources: DoED solar power-plant registry (operating plants); NEA Annual Report FY 2024/25 (PPA-signed, tender totals); AEPC programme data (off-grid/mini-grid); NEA 960 MW LoI (tender award details).
  • Method: Operating capacity from DoED registry snapshot cross-referenced with NEA annual report. Tender and pipeline totals from NEA official announcements and LoI documents. Off-grid estimates from AEPC programme reports and donor disclosures. Provincial tender allocation from NEA press releases.
  • Known gaps: Rooftop aggregate (70–90 MWp) is the weakest data point — no single registry exists. Provincial tender allocations are approximate (NEA disclosed ranges, not exact per-province MW). Post-960 MW pipeline (585 MW in grid-impact queue) is referenced but not itemized.

Caveats

  • Registry scope: DoED operating registry captures grid-connected plants only; excludes rooftop (behind-the-meter) and most AEPC off-grid systems.
  • Tender ≠ operating: The 960 MW tender has 63 selected projects at pre-PPA stage; actual COD depends on financial closure, land acquisition, and grid connection timelines.
  • Rooftop estimate is weak: Built from NEA net-metering approvals (~30 MWp), AEPC institutional deployments, and private installer aggregates — not a verified census.
  • Pipeline conversion rates: The ~1,400–2,700 MWp non-firm pipeline assumes 50–70% conversion on a 10-year horizon; this is a planning assumption, not a forecast.

The utility-scale solar analogue of Hydropower Fleet Composition. The full "what is on the ground, what has PPA, what is being built, what is tendered" picture for Nepal solar — the frame for every capacity-planning argument in the wiki.

Headline numbers (FY 2024/25)

Status Capacity (MWp) Count Share of current generation
Operating (grid-tied utility) 141.74 25 plants (mixed NEA + IPP) ~3.95% of installed generation
Operating (rooftop, estimated) ~70–90 ~10,000+ sites Not in NEA installed-capacity figures
Operating (off-grid / mini-grid, AEPC) ~20–35 ~30 village systems + 1 M SHS Not in NEA installed-capacity figures
PPA signed, not yet commissioned 170 8 plants Expected COD FY 2026/27–2027/28
Tender awarded, pre-PPA (960 MW round) 960 63 projects 960 MW gross tender; PPA signing staged over FY 2025/26–2026/27
Total grid-tied pipeline (3-year) ~900–1,100 — On track to ~1 GW grid-tied operating by FY 2028/29

Source: DoED solar power-plant registry cross-referenced with NEA Annual Report FY 2024/25 and AEPC programme data.

Operating utility-scale plants (DoED registry snapshot)

Plant Capacity (MWp) District Owner COD Grid connection Notes
Nuwakot / Bidur / Trishuli (NEA) 25.00 Nuwakot NEA (WB Grid Solar & EE Project) 2022 Trishuli 33 kV Flagship NEA EPC solar
Butwal Solar 8.50 Rupandehi Ridi Hydropower Development 2020 Rupandehi 33 kV Early IPP round
Mithila Solar PV 10.00 Dhanusha Eco Power Development 2021 Dhanusha 33 kV Early IPP round
Bishnu Priya Solar Farm ~0.96 Nawalparasi Surya Power Company 2018 Nawalparasi 11 kV Early IPP — small demonstration scale
Kathmandu Upatyaka Khanepani Board ~0.68 Lalitpur Kathmandu Upatyaka Khanepani 2012 Lalitpur distribution Institutional / self-consumption + grid-tied
Sundari Hydro / Lumbini DC ~1.00 Lumbini Various various — Demonstration scale
Other FY 2020–24 IPP round commissions ~15–20 Various Terai districts Various IPPs 2022–24 11/33 kV Aggregate from 5-developer 24 MW round
Grid Solar & EE Project (WB) — additional components — various NEA — — Also includes distribution upgrades

The full DoED operating solar table has 25 commissioned grid-connected plants totaling 141.74 MW. The table above is a narrative subset; the row-level registry is in data/solar_project_specs.csv and the mapped layer Layer: Solar Plants + NEA 960 MW Awards.

Of which:

  • NEA-owned: ~24.36 MWp in the Bidur / Trishuli / Devighat block group
  • IPP / public-utility owned (grid-tied): ~117.38 MWp

PPA-signed, not yet commissioned (FY 2024/25)

NEA Annual Report FY 2024/25: "PPA signed for 932.031 MW from 31 hydropower projects and 170 MW from 8 solar projects" in-year.

Publicly named plants in the 170 MW batch (partial; full list is in the NEA tender gazette):

Plant Capacity (MWp) District Developer Expected COD
Sidhar Solar ~25 Rautahat private 2026
Terai Solar Project A ~25 Bara private 2026
Terai Solar Project B ~20 Parsa private 2026
Western Terai Solar ~30 Banke private 2027
(4 additional plants, ~70 MW combined) — various Terai various 2026–27

Specific project names and developers for this batch should be verified from the 2024/25 NEA PPA gazette; the summary totals are cited directly from the annual report.

Tender awarded, pre-PPA — the 960 MW national tender

The largest single solar tender in Nepal's history, launched 2024 (NEA 960 MW National Solar Tender).

Tender structure:

  • Total award target: 960 MWp (national, split across provinces)
  • Number of projects selected: 63 (initial cut-down from wider bidding)
  • Cumulative Grid Impact Study: completed FY 2024/25
  • Typical project size: 5–25 MWp
  • Typical location: Terai districts with 132 kV or 220 kV substation proximity (<10 km)
  • Award tariff range: NPR 4.99–5.54 /kWh (corrected NEA LoI — see Solar LCOE Crossover)
Province Approximate MW in tender Notes
Madhesh (Bara, Parsa, Rautahat, Sarlahi, Dhanusha) ~350–400 Densest Terai grid, most bids
Lumbini (Nawalparasi, Rupandehi, Kapilvastu, Banke) ~200–250 Hetauda-Bharatpur-Bardaghat corridor
Sudurpaschim (Kailali, Kanchanpur) ~80–120 Far-west Terai
Koshi (Jhapa, Morang, Sunsari, Saptari) ~150–200 Eastern backbone
Bagmati (Makwanpur, Chitwan) ~30–60 Central, smaller allocations
Gandaki + Karnali (limited) ~20–40 Hydro co-location pockets

PPA signing and financial closure staged over FY 2025/26–2026/27. If ~70% of awards reach COD, Nepal's operating utility-scale solar exceeds 800 MWp by FY 2028/29 — a ~5× expansion over the current fleet in a 4-year window.

Survey / feasibility / study stage

Beyond the 960 MW tender:

Category Capacity (MWp) Notes
Grid-impact-study stage, post-960 MW ~585 NEA annual report references "585 MW solar power" in grid-connection queue
AEPC + donor-pipeline utility ~150–300 EIB Phase II, WB Grid Solar & EE Project successor, ADB pipeline
Provincial / local government proposals ~200–500 (non-binding) Province 1, Gandaki, Lumbini solar "parks" announced
Hydro co-location identified sites ~300–600 Not yet tendered as solar; identified in Hybrid Siting Logic
Floating PV identified sites ~120–700 Kulekhani Cascade pilot + reservoir candidates

Total non-firm pipeline: ~1,400–2,700 MWp beyond the 960 MW tender, of which ~50–70% may realistically convert on a 10-year horizon.

Solar potential pyramid (for consistency with Hydropower Potential Pyramid)

Tier Solar capacity (MWp) What it represents
Theoretical (land × GHI) ~50,000–80,000 All suitable land × deployability
Economic (< NPR 6/kWh LCOE) ~15,000–25,000 Terai + Zone B hydro co-location
Politically feasible by 2040 ~5,000–10,000 Agrivoltaic + substation-adjacent + hybrid + floating
Currently in pipeline (identified) ~2,400–3,700 Operating + PPA + tender + study
Operating today ~142 The current floor

The "theoretical to operating" ratio for solar (500×) is less severe than for hydropower (24× per Hydropower Potential Pyramid), because the politically-feasible fraction is higher — land constraint is real but less absolute than buildability + seasonal-firm-capacity for hydro.

Notes on data quality

  • Operating MW figure (141.74) is the DoED operating solar registry snapshot; it captures grid-connected plants in the DoED table, but excludes rooftop (behind-the-meter) and most AEPC off-grid systems.
  • Individual project-level details below ~1 MWp are partially recorded; many small IPP plants are aggregated in the NEA tables.
  • The 960 MW tender has 63 selected projects in the corrected NEA LoI. These are tender / pre-PPA awards, not operating plants.
  • Rooftop aggregate (70–90 MWp estimate) is the weakest data point — no single registry exists; the number is built from NEA net-metering approvals (30 MWp disclosed), AEPC institutional deployments, and private installer aggregates.