Nalsyau Gad
- Page status
- Working page
- Updated
- 2026-05-13
Nalsyau Gad is a 410 MW storage candidate in the Karnali basin and the best dry-energy performer in the JICA promising-storage set used by this wiki. It is pinned in both Layer: Storage Shortlist and Layer: Priority Watchlist because it contributes the kind of dry-season energy Nepal's run-of-river-heavy system is missing.
Summary
Nalsyau Gad is a 410 MW JICA promising-storage candidate in the Karnali basin and the best dry-energy performer in the JICA shortlist used by this wiki, with 581.8 GWh dry-season energy (41.4% dry share). It is pinned in both the storage shortlist and priority watchlist. The page tracks it as a dry-season portfolio option using the JICA/NEA source set.
Specifications
| Parameter | Value |
|---|---|
| Capacity | 410 MW |
| Status | Survey / study |
| Category | jica promising storage |
| Basin | Karnali (Karnali Basin) |
| Annual energy | 1406.1 GWh |
| Dry-season energy | 581.8 GWh |
| Dry share | 41.4% |
| Total storage | 419.6 MCM |
| Effective storage | 296.3 MCM |
Storage
| Parameter | Value |
|---|---|
| Total storage | 419.6 MCM |
| Effective storage | 296.3 MCM |
Output
| Parameter | Value |
|---|---|
| Annual design energy | 1406.1 GWh |
| Dry-season energy | 581.8 GWh |
| Dry-season share | 41.4 % |
| Type | Storage |
Sources
Why It Matters
Nalsyau Gad's value is not just its 410 MW nameplate. The JICA/NEA storage-screening figures give it 581.8 GWh of dry-season energy, equal to 41.4% of annual energy. That is the strongest dry-energy output in the promising-storage shortlist and one of the few project records that directly addresses the Storage Deficit rather than only adding wet-season energy.
Shortlist Context: How Nalsyau Gad Compares
Among the JICA promising-storage candidates in the wiki, Nalsyau Gad occupies a unique position — highest dry-energy share by a significant margin:
| Project | MW | Annual (GWh) | Dry (GWh) | Dry Share | Effective Storage (MCM) |
|---|---|---|---|---|---|
| Nalsyau Gad | 410 | 1,406.1 | 581.8 | 41.4% | 296.3 |
| Kokhajor-1 | 112 | 278.9 | 94.1 | 33.7% | 166.1 |
| Madi | 200 | 621.1 | 170.7 | 27.5% | 235.1 |
| Naumure (W. Rapti) | 245 | 1,157.5 | 309.9 | 26.8% | 580.0 |
| Lower Badigad | 380 | 1,366.0 | 354.7 | 26.0% | 505.5 |
| Chera-1 | 149 | 563.2 | 120.6 | 21.4% | 141.1 |
| Andhi Khola | 180 | 648.7 | 137.1 | 21.1% | 238.7 |
| Lower Jhimruk | 143 | 454.7 | 94.4 | 20.8% | 211.6 |
| Sun Koshi No.3 | 536 | 1,883.6 | 335.9 | 17.8% | 555.0 |
What makes the 41.4% figure significant is that it approaches the dry-share range of seasonal-storage projects with much larger reservoirs. Kulekhani Cascade achieves ~50% dry share with only 106 MW. Budhigandaki Hydroelectric Project projects 42% at 1,200 MW with 3,300 MCM of total storage. Nalsyau Gad is delivering comparable dry-energy concentration with less than one-tenth the reservoir volume of Budhigandaki and at a capacity point that is commercially viable for domestic financing.
This is why it appears in the priority watchlist despite being survey-stage. A project can be strategically important before it is construction-ready if it changes the dry-season balance, especially in a system where Kulekhani Cascade is still the only operating seasonal-storage anchor and Tanahu Hydropower Project is the only large storage project in active construction.
Reservoir Economics
Nalsyau Gad's 296.3 MCM effective storage on 410 MW yields a storage-to-capacity ratio of 0.72 MCM/MW — lower than Naumure (2.37 MCM/MW) or Sun Koshi No.3 (1.04 MCM/MW), but the project achieves its high dry share through a different mechanism: favourable basin hydrology in the upper Karnali catchment rather than sheer reservoir volume. The Karnali basin receives reliable monsoon precipitation and has a less flashy dry-season recession than eastern basins like the Koshi, meaning a moderate storage volume can achieve proportionally more dry-season firming.
This hydrological advantage is partly why the Karnali basin dominates the JICA shortlist: 6 of the 9 candidates (Nalsyau Gad, Lower Badigad, Naumure, Madi, Andhi Khola, Chera-1) are Karnali-basin projects. The basin's flow regime is intrinsically more storage-friendly.
Status And Timing
Nalsyau Gad should be read as a planning / promising-storage candidate, not a confirmed near-term build. The IPSDP milestone ladder groups Nalsyau Gad STO in the 2031-2035 project window. That is a planning sequence, not a construction contract.
Near-term milestones that would need to occur:
- Feasibility study update — the JICA IPSDP provides screening-level data; a bankable feasibility study is the next technical gate
- Developer assignment — currently no developer is designated (unlike Dudhkoshi/NEA or Tanahu/NEA). VUCL (Vidhyut Utpadan Company Limited) is the most likely candidate given its mandate for Karnali-basin storage (Mugu Karnali Storage HEP, Phukot Karnali)
- Environmental and social screening — the Nalsyau Gad catchment requires baseline data on resettlement footprint, downstream water-use impacts, and biodiversity
- Financing structure — whether this follows the NEA/AIIB sovereign model (Dudhkoshi), the VUCL/PPP model (Mugu Karnali), or a new structure
- Transmission evacuation — routing from the upper Karnali catchment into the western hill grid and ultimately to the 400 kV backbone. See Nepal Transmission System — 400 kV Landscape & Cross-Border Plan (2025)
Transmission & Grid Integration
Nalsyau Gad's location in the upper Karnali catchment presents a transmission challenge. The western Karnali region has limited 220 kV connectivity; the nearest 400 kV infrastructure is the proposed Karnali corridor. A 410 MW storage plant in this location would require:
- A dedicated 220 kV transmission line from the powerhouse to the nearest substation
- Integration with the planned Karnali basin transmission backbone (linked to Upper Karnali and Mugu Karnali Storage HEP evacuation plans)
- Possibly a collector substation serving multiple Karnali storage projects (Nalsyau Gad, Lower Badigad, and Madi are all in the same general catchment)
The transmission constraint is not a deal-breaker — 410 MW is within the range of standard 220 kV double-circuit capacity — but it adds a material cost component that the JICA screening-level cost estimates may not fully capture. Transmission costs for western hill storage are consistently higher per km than eastern corridor equivalents.
Geological & Site Character
The Nalsyau Gad site is in the upper reaches of the Nalsyau Gad river — a Karnali tributary draining the southern flank of the Saipal Himal range in far-western Nepal. The JICA screening identifies the site as having suitable dam-axis topography for a storage reservoir with ~420 MCM total capacity, suggesting a relatively wide valley section upstream of a constriction — the classic storage-dam site geometry.
Key geological considerations include:
- Himalayan foothill geology — sedimentary and metamorphic rock formations typical of the Lesser Himalayan zone, with potential for weak interbedded shales
- Seismic zone 4+ — within the active Himalayan deformation front
- Sediment load — the Nalsyau Gad drains steep terrain; sediment management in the reservoir design will be critical for maintaining active storage volume over the project life. See Sediment as Design Constraint
- GLOF exposure — lower than the Dudh Koshi or Arun basins, but the upper Karnali has glacially-fed tributaries that require assessment
Limitations & Controversies
- Survey-stage data only. The JICA IPSDP figures are screening-level, not bankable. A full feasibility study could shift capacity, energy, or storage numbers materially.
- No developer assigned. Unlike Dudhkoshi (NEA), Tanahu (NEA), or Mugu Karnali (VUCL), Nalsyau Gad has no institutional sponsor moving it forward.
- Transmission cost uncertainty. The western hill grid is less developed than the eastern and central corridors. Evacuation from a remote Karnali tributary adds cost.
- Competing Karnali priorities. The Karnali basin has multiple storage candidates vying for limited development bandwidth: Mugu Karnali (1,902 MW, pre-construction), Phukot Karnali (426 MW, survey), Upper Karnali (900 MW, stalled), Karnali Chisapani (10,800 MW, conceptual). Nalsyau Gad must compete for developer attention, financing, and transmission capacity with larger projects.
- Downstream water-use impacts. The Nalsyau Gad feeds the Karnali main stem; flow alteration could affect downstream ecosystems and, potentially, cross-border flows into India's Ghaghara system. See Hydro-Geopolitics.
Map Interpretation
The map marker is a river-aligned project reference derived from the registry/project point. It is suitable for basin-level and corridor-level comparison, but it should not be treated as a final dam-axis coordinate.
Registry note
- JICA/NEA storage master plan volume 2
See also
- Karnali Basin
- Storage Deficit
- Firm Power
- IPSDP Milestone Ladder 2022-2040
- Layer: Storage Shortlist
- Layer: Priority Watchlist
- Mugu Karnali Storage HEP — the largest Karnali storage project
- Sediment as Design Constraint